Process: obtaining the License to Sell; (we got one for HGGMP at last for 27,000 plots after spending nearly P10 million

Providing outstanding amazing values through process clarity and improvement 


Congratulations for the issuance of License to Sell to Luis Project Officer,, the absence of which was the excuse for non selling  of HGGMP.  The processes list for this rather short:
                                                                                                       Keypoints
                Tasks/Steps
1.  Survey (topo)                                                        1.  The area of 11 hectares was steep, bangin
                                                                                   2.  It was populated by nearly a hundred illegal
2.  Preparation of SDP                                                   settlers



3.  Approval of the SDP                                             1.  Consider former creek and Andrea
                                                                                   2.  Barangay clearance required +  rc

4.  Barangay clearance                                              1.  RE for squatters removal and OK for SB                                            
                                                                                        Resolution

5.  Sangguniang Pansiyudad approval                        1.  Coordination with Planning office
                                                                                     2.  RE in the high 7 numbers, kaliwaan

6.  Engaging a contractor                                           1.  Previously 4 years ago
                                                                                    2.  Nego for escalation
                                                                                    3.  Wait for removal of squatters
                                                                                    4.  Have to deal with difficult terrain

7.  Contract for verified survey return                        1.  A requirement by EO 648 
                                                                                    2.  High 6 numbers

8.  Filing with DHSUD                                              1.  Constant follow up
                                                                                   2.  Right connection
                                                                                   3.  Concern is the bond amount which 
                                                                                              was upped for the com of agents
9.  Estimate of bond, payment of bond

10.  Filing of VSR                                                     1.  Full payment of pf

11.  Paying of the fees amounting to P2M                1.  By MC

12.  Issuance of LTS CR   (9/3/2025)

For 4 and 5 we had to fork out representation expense (which we hope will not happen again because the NBI nabbed LGU officials for such a crime  For all in all we spent about 9 to 10 m to get these things done

We now motivate HGGMP office and marketing group to Sell at least a 1,000 by year end