Re: Documentation of project status (PROJECT STATUS REPORT)

Please see Project Report for August 2026

 Projects Status Report as of July 2026   by Luis Sanchez 
 Budget   Actual   Actual   Cumulative 
 Project   Days to Complete   Days as of Today   Amount Paid  % Completion  Cost to Complete   Comments/Difficulties/Solutions 
 HGGMP Chapel Renovation   Chapel already rented out this week 
 Renovation                           85,000                                 90 -                              30                     65,280 95%                         19,720  Completed, minor repairs needed for gutter to prevent water seepage  
 Furniture and equipment                                  15                                   7 100%                                  -    Delivered all furniture and appliances 
 Building Permit                         120,000                                 30                                 30                       9,000 100%                       111,000  Completed, coccupancy permit for submission next week.  
 Meralco connection                           50,000                                 30                                  -                                -   0%                         50,000  May only be processed upon completion of Occupancy Permit 
 HGGMP Land Development                   48,500,000                              540                              240                7,959,364 18%                 40,540,636  Billing No. 2 requested waiting for release 
 HGGMP Emblaming and Casket Display 
 Renovation                         285,000                              180                              240                   218,880 80%                         66,120  Materials were stolen so we had to put up aluminum roll up doors 
 Furniture and equipment                         200,000                                 15                                 37 0%                       200,000  Amount for canvassing, possible contractor is Collidge from Valenzuela 
 HAMP Electrification 
 Preparation Works                         460,000                                 45                                  -                                -   0%                       460,000  Recommend award to GERB's Electrical Trading. Waiting for DP check release 
 Payment to MERALCO                         188,550                                 14                                  -                                -   0%                       188,550  May only be paid upon inspection of preparation works (service entrance post, panel baord instalaltion) 
 Change of electrical plan                      1,250,000                                 45                                  -                                -   0%                   1,250,000  Will be bid out upon completion of preparation works, initial proposal is 1.25M 
 HAMP Phase 2 LTS 
 Development Permit                         609,560                                 90 -                              90                   359,560 90%                       250,000  Resolution by Morong LGU for ratification in Provincial Office was returned due to differences in areas for application and absence of signature of Mayor who was on leave during the deliberation of Dev Permit resolutoin 
 HAMP Phase 1 Alteration                             5,000                                 30                                  -                                -   50%                           5,000  Need to alter Phase 1 SDP since portion of JBA property is included in Phase 2 Masterplan 
 Revised SDP                                    -                                   15                                  -   0%                                  -    Will ask Engr. Marcelino to revise SDP 
 Letters to Buyers                             7,000                                   7                                  -                                -   50%                           7,000  Requested budget for initial 100 letters to buyers, letter for printing 
 License to Sell and COR                                   -  
 Publication                           23,000                                 15                                  -                                -   0%                         23,000  For request upon release of Notice to Publish 
 Signed and sealed Fact Sheet                                    -                                     3                                   3                              -   100%                                  -    Prepared and signed 
 Performance Bond                           49,803                                   7                                  -                                -   0%                         49,803  For request upon release of Notice to Post Bond 
 Inspection Fee                             1,500                                   1                                  -                                -   0%                           1,500  For request upon release of Notice to Publish 
 Processing Fee                         118,610                                   1                                  -                                -   0%                       118,610  For request upon release of Notice to Publish 
 LTS Forms                                 432                                   1                                  -                                -   0%                              432  For request upon release of Notice to Publish 
 Verified Survey Returns                         230,000                              120                                 30                     69,000 30%                       161,000  DP released plan for submission to DENR LMB 
 Release of LTS 
 HAMP Columbarium LTS 
 Adjustment of Ash crypts                         225,000                                 30                                  -                                -   0%                       225,000  To be adjusted if DHSUD inspects 
 Development Permit Columbarium                                   -  
 Development Permit Fee                           26,425                                   1                                   1                     26,425 100%                                  -    Paid DP Fee but we need to comply with additional requirements 
 HAMP Phase 1 Alteration                             5,000                                 15                                  -                                -   50%                           5,000  Need to alter Phase 1 SDP to confirm parking standards are met 
 CR and Chapel Plans                                    -                                   15                                  -                                -   0%                                  -    Need to provide chapel, CR and Office plans 
 Columbarium LTS and COR                                   -  
 Publication                           23,000                                 15                                  -                                -   0%                         23,000  For request upon release of Notice to Publish 
 Signed and sealed Fact Sheet                                    -                                     3                                   3                              -   100%                                  -    Prepared and signed 
 Performance Bond                           20,000                                   7                                  -                                -   0%                         20,000  For request upon release of Notice to Post Bond 
 Inspection Fee                             1,500                                   1                                  -                                -   0%                           1,500  For request upon release of Notice to Publish 
 Processing Fee                           72,576                                   1                                  -                                -   0%                         72,576  For request upon release of Notice to Publish 
 LTS Forms                                 432                                   1                                  -                                -   0%                              432  For request upon release of Notice to Publish 
 Release of LTS 
 HMMG Rivera SDP 
 SDP Approval                           60,000                                 30                              150                              -   50%                         60,000  Amount for negotiation, lower to 40K 
 HMMG Land Development 
 Land Dev Punchlist                         421,484                                 60 -                            150                              -   50%                       421,484  Pathwalk, cul de sac and parking demolished but is yet to be rectified. Engr. Joey told us he is unable at the moment due to heart condition 
 Steel Gate                         123,000                                 60 -                            150                              -   0%                       123,000  Requested but no approval yet 
 Steel Signage                         115,000                                 60 -                            150                              -   0%                       115,000  Requested but no approval yet 
 Water and Power lines                           60,000                                 30 -                            150                              -   0%                         60,000  Requested but no approval yet 
 Comfort Room Chapel                         875,000                                 90 -                            150                              -   0%                       875,000
 HGOMP 
 Roads and Pathwalks                      2,240,000                              120 -                            240                1,987,952 100%                       252,048  Completed 
 Main Chapel                      1,300,000                              120 -                            240                   794,006 40%                       505,994  Roof just installed, finishing works on-going 
 Admin Office                      1,600,000                              120 -                            240                1,432,338 100%                       167,662  Completed, furniture for purchase 
 Entrance Renovation                         400,000                              120 -                            240                   343,319 100%                         56,681  Completed 
 Public CR                         200,000                              120 -                            240                   175,265 100%                         24,735  Completed 
 Bereavement Chapel                      2,240,000                              120 -                            240                   928,187 30%                   1,311,813  Civil works on-going 
 HGCMP Land Development 
 Site Clearing                           30,000                                 20 -                              15                     22,500 80%                           7,500  Site cleared of grass, needs to be cleared of trees 
 Land fill                   11,000,000                                 90                                  -                                -   0%                 11,000,000  5500 per truckload (15 cum) for negotiation 
 HGSCMP Renovation 
 Repainting of Entrance Fence                         545,100                                 30                                  -                                -   0%                       545,100  Negotiate to 388,105.25 
 Repair & Renovation of Guard House                         415,300                                 30                                  -                                -   0%                       415,300  Negotiate to 262,601.625 
 Repair & Renovation of Office and Chapels                      2,562,200                                 60                                  -                                -   0%                   2,562,200  Negotiate to 1,780,104.625 
 Repainting of Crematorium                         136,400                                 30                                  -                                -   0%                       136,400  Negotiate to 312,329.875 
 Construction of Garage Shed                         270,000                                 30                                  -                                -   0%                       270,000  Negotiate to 264,290 
 HGSCMP Landfill 
 Batch 1                         470,000                                 15                                 15                   470,000 100%                                  -    Fully delivered and paid. Converted into 932 lots 
 Batch 2                         450,000                                 15 -                              35                   180,000 88%                       270,000  87 out of 100 trucks delivered, to be converted into 756 lots 
 Batch 3                         450,000                                 15                                  -                                -   0%                       450,000  For scheduling, will be converted into 203 lots 
 HGLUMP 
 Storage Room Construction                         220,000                                 30                                  -                                -   0%                       220,000  Budget for approval and release 
 Office and Chapel Repair                         150,000                                 30                                  -                                -   0%                       150,000  Budget for approval and release 
 Site Beautification                           75,000                                 30                                  -                                -   0%                         75,000  Budget for approval and release 
 HGMMP Site Works 
 Land Development                   37,550,000                              720                              570             16,080,112 21%                 21,469,888  On-going, long hault from December to present 
 Office Construction                      1,500,000                                 90                                  -                     450,000 0%                   1,050,000  Pending building permit application 
 Steel Gate                         300,000                                 30 -                            510                     90,000 0%                       210,000  Not yet started, contractor is looking for welder 
 Guardhouse                         650,000                                 60                                 60                   351,000 95%                       299,000  Almost complete 
 HGMMP Legals 
 SEC Registration                             5,000                                 15 -                              40                       1,200 75%                           3,800  Change in corporate structiure need to look for incorporators 
 Transfer Ownership of Property                                   -  
 DOAS                             5,000                                   1                                  -                                -   50%                           5,000 Title to be transferred to New Dev Company
 CAR                             1,300                                 15                                  -                                -   0%                           1,300 To be processed upon Incorporation of Dev Company
 Transfer Tax                                    -                                     2                                  -                                -                                -                                    -   To be processed upon Incorporation of Dev Company
 DAR Clearance                      1,079,400                                 30                                  -                                -                                -                     1,079,400 To be processed upon Incorporation of Dev Company
 Release of title                         269,850                                 20                                  -                                -                                -                         269,850 To be processed upon Incorporation of Dev Company
 Development Permit                                   -  
 Barangay Clearance                                   -   Budget may not be necessary with assistance of supplier Jong Valdez
 Zoning Clearance                             3,500                                   3                                   3                       3,500 100%                                  -   Completed
 DOH initial clearance                           10,000                                 30                                  -                                -   100%                         10,000 For inspection of DOH Regional Office. Resolution corrected already by SB Secretary
 DAR Conversion Order                         150,000                              120                                  -                                -   20%                       150,000 DOAS need to be notarized first. Dianne Cabrera submitted a proposal for Php 150K professional fee for 2 months
 Water Permit from NWRB                             7,500                                 15                                  -                                -   20%                           7,500 To be processed upon completion of DAR Conversion (to be verified if may be undertaken) and DOH initial clearance
 Development Permit Fee                           50,000                                 30                                  -                                -   20%                         50,000 To be processed upon completion of DAR Conversion (to be verified if may be undertaken) and DOH initial clearance
 License to Sell and COR                                   -  
 Duly audited balance sheets                                    -                                     3                                  -                                -   0%                                  -   May submit Affidavit instead of financial documents
 Publication                           23,000                                 15                                  -                                -   0%                         23,000 To be requested upon Notice to Publish
 Performance Bond                           95,445                                   7                                  -                                -   0%                         95,445  For request upon release of Notice to Post Bond 
 Certificate of Registration                             2,880                                   1                                  -                                -   0%                           2,880  For request upon release of Notice to Publish 
 Inspection Fee                             7,500                                   1                                  -                                -   0%                           7,500  For request upon release of Notice to Publish 
 Processing Fee                         829,440                                   1                                  -                                -   0%                       829,440  For request upon release of Notice to Publish 
 LTS Forms                                 432                                   1                                  -                                -   100%                              432  For request upon release of Notice to Publish 
 Verified Survey Returns                         250,000                              120                                  -                                -   0%                       250,000  For quotation 
 Release of LTS 

On Tue, Aug 25, 2026 at 3:19 PM Jorge Saguinsin <jorge@holygardens.ph> wrote:
 Please summarize in succinct form big letters:  (thank you as of Aug 15)

BAKA PUWEDE MAY MABAGO MAY ACTION.    in my books action and execution count...  Principles 1 and 2.  What are they?
                                                                  Previous Status                                 Update
    1.     Hamp   

           1.  Electrical
           2.  Talanay

                 TIA
                 DP

                 LTS
                 construction

      2.   HMMG

             1.  Electrical
             2.  CR
             3.  Rivera design
             4.  Gate       

     3.   Malasiqui

           1  Articles of Inc.
           2. Stockholders
           3.  Transfer
           4.  LTS docs
          5.  Office of Malasiqui
          6.  Flaglets
          7.  Brushcutter  of site
         8.  Resumption of construction...

   4..  SSC

        1.  Guardhouse repair
        2.  Columbarium repair
        3.  Office repair
        4.  Interior redesign

5.  HGGMP

      1.  2nd floor repair
      2.  Main chapel repair

    UNDER REMARKS INDICATE WHEN WHAT HOW YOU ARE GOING TO DO

6.  Calapan

      1.  Bids
      2.  Resumption of construction

7.  Oton

    1.  Chapel comp;etion

On Tue, Jul 28, 2026 at 3:38 PM Luis Sanchez <llsanchezjr@gmail.com> wrote:
Sorry for delay, please see attached file.

image.png
image.png
image.png
image.png
image.png
image.png


On Fri, Jul 24, 2026 at 5:44 AM Jorge Saguinsin <jorge@holygardens.ph> wrote:
May we implement for the RECORD documents supporting our project status:    (Every month 5 days after end of previous month)

                                                                                      Projects Status Report as of ________________________
                                                                                     by Project Officer/   Contractor 

(Please format in excel)

 EXISTING


Project location title                         
                                                                                                     Actual                                                         Actual                                    Cumulative                         Comments/difficulties/solutions
    Sub items                Cost           Days to complete          Days as of today     Amount as of todate         % completion      Cost              Completion
                       
   1
   2.
   3.   


PLANNED
    

Prepared by ______________________________________Date ____________________NOted by ________________________________________

cc:    Accounting/Ms. Madel  

-x-x-x-x-x-

    Contractor:

    1.  Malasiqui

    2.  Oton  

   PO

    Existing

   1.  Calamba

  2.  Malasiqui

 3.  HMMG
  
   Planned   (Ibang format ang kailangan)

  1.  Talanay

  2.  Rivera

 3.  Calapan

4.  Oton Iloilo  (1 hectare






PLEASE CONFIRM REQUESTED MEETING TODAY  CONFIRMED BY Engr.  Fort, 4 pm at Angono Jollibee